Chattanooga, TN

Hamilton County Septic Permits: What Homeowners Need to Know

Hamilton County runs its own septic program as a TDEC contract county. You deal with Groundwater Protection, inside the county's Development Services department, rather than a TDEC field office. The program issues permits for new systems and for changes to existing ones, and it follows TDEC standards for subsurface sewage disposal.

This page summarizes official county and TDEC information checked on Nov 20, 2026. Fees and rules change. Confirm current details with Groundwater Protection before you apply or before any work starts. This site is a referral service, not the county, and not a septic contractor.

Who to call, and where they sit

Hamilton County Groundwater Protection 1250 Market Street, Suite 3046 Chattanooga, TN 37402 Phone: 423-209-7876 Email: gwp@hamiltontn.gov Hours: 8 to 4:00 PM. The county asks you to arrive by 3:30 PM if you are applying in person for a permit or taking an installer test.

Email or call that office about new septic installation, use of an existing system (additions, pools, accessory buildings, garages), lot reviews, septic repairs, swings and other playground equipment, water sample testing (spring or well), and complaints of malfunctioning septic systems.

For sewer line (street connection) information, the county points you to the Hamilton County Water and Wastewater Treatment Authority (WWTA) at 423-209-7842. WWTA is in the same building, Suite 3050. WWTA is not the septic permit office, and it is not responsible for sewers inside the City of Chattanooga, the City of Collegedale, or the Town of Walden. Inside the City of Chattanooga, sewer questions go to 311 or (423) 643-6311.

The Development Services main desk, a different number, is 423-209-7970.

Applications are online

All Groundwater permits have had to be submitted online since March 11, 2024. The county's septic information page says all applications must be completed online. Start from the county's Development Services or Septic Information pages, which point to the online application.

Current Groundwater fees

These figures are from the live Development Services page, checked Nov 20, 2026, and are tied on that page to Groundwater Fee Change Resolution 423-28:

  • New Permit: $440.00
  • Modification: $440.00
  • Repair Permit: $40.00
  • Existing Permit: $205.00
  • STVR Inspection: $205.00
  • Lot Review: $150 per lot plus a $5.00 application fee
  • Inspection Letter: $105.00
  • Water Testing: $105.00
  • Recertification Letter: $180.00
  • Re-inspection (starting for a 3rd visit): $150.00

Some older county PDF forms still print an Existing Permit fee of $200.00 and an older office suite number. This page follows the live fee list and the live address, Suite 3046. If you are looking at a printed form and the fee disagrees with the website, ask the county which figure is current.

The county also lists installer license fees: $200.00 for a Category 1 (standard) installer license, and $100.00 for each additional license (alternative or experimental). Installers are required to have a county septic installer license. Someone who already holds a state installer permit still applies and pays the fee, but does not have to take the county test. The Hamilton County installer permit is good for one year. The county publishes a list of licensed septic installers and pumpers on its septic information and Development Services pages.

Which permit is which

The county's own table is the clearest guide:

  • New conventional septic system for a house, shop, barn, or commercial building: New Septic Permit.
  • New alternative septic system (LPP, mound, and similar): New Septic Permit.
  • Modify an existing system to add bedrooms, or add field lines: Modification.
  • Repair an existing system: Repair.
  • Preliminary plat approval for septic: Lot Review.
  • Addition of a pool or barn with no plumbing: Existing Permit.
  • Water tested for bacteria (total or fecal coliform): Water Sample.

Setbacks when you add on to a house

The county's Application for Use of Existing Septic System says:

  • Any addition to a residence must be at least 5 feet from the septic tank and 10 feet from the field lines.
  • In-ground pools, or additions that require the existing grade to be cut more than one foot, must have a 25-foot setback from the field lines.
  • If a bedroom is being added, the applicant may be required to modify the existing system so that it meets the field-line footage requirements in the state regulations.
  • You may be required to obtain a soils map from an approved soil consultant.

Stake out the building or addition as the form instructs, then apply. Confirm these distances with Groundwater Protection if your project is unusual, or if you are working from an older printed form.

Records of an existing system

Property owners who need a copy of an existing septic tank permit or an installation certificate of completion should email gwp@hamiltontn.gov. Other requesters should use the county's document retrieval tool (hamiltontn.gov, Online Services, Building Inspection App, Document Retrieval). Search by street name only; do not enter the street number. If the address is not listed, email Groundwater Protection. More on using those records is on finding a buried tank.

The fee list includes an Inspection Letter at $105.00 and a Recertification Letter at $180.00. The pages that were checked do not spell out what each letter contains. If you need a letter for a sale, a lender, or a refinance, ask the county what it includes and whether it is the document your lender wants. A private inspection is a separate service. See septic inspection.

Third-party permit packages, starting October 1, 2024

Tennessee Code Annotated 68-221-403(m) lets a person use a third-party water resources engineer to prepare a permit package, and in some cases to conduct the final inspection, in lieu of the department or the contract county. A soil scientist certified by the department may submit an application for a system under 750 gallons per day. TDEC lists Hamilton among the contract counties, so those packages should be submitted directly to Hamilton County, in the form the county requires. The department or the county then has ten business days after receipt to approve, reject with a deficiency report, or request more information. Details are on TDEC's third-party permits page and are summarized on new septic systems.

Official pages to keep bookmarked

Related pages

FAQ

Do I still walk into the Groundwater office to apply? Routine Groundwater permits have been online only since March 11, 2024. The office is still there for questions, records, installer tests, and the situations the county describes. Call 423-209-7876 or email gwp@hamiltontn.gov if you are unsure how to file.

Is the repair permit really $40? That is the figure on the live fee list checked Nov 20, 2026. Confirm it when you apply, because fee schedules change.

Who keeps the list of licensed pumpers and installers? Hamilton County Groundwater Protection. The list is linked from the county's Septic Information and Development Services pages.

If you want a local professional to talk through the work and the permit, call (423) 225-8134 or send a request. The permit itself still comes from the county.

Not sure what your system needs? Just ask.

Call (423) 225-8134